Opening day should smell like fresh tortillas or brisket, not wet drywall and missed inspections. The fastest way to get from lease to ribbon-cutting is a clean, logical build-out plan that your landlord, architect, contractors, and inspectors can all say “yes” to. Below is a field-tested checklist tailored for Lubbock restaurant projects—from permitting to final health sign-off—so you can open faster and avoid costly rework.
Step 1: Pre-Lease Due Diligence (Before You Sign)
-
Zoning & Use: Confirm the address allows restaurant use (and alcohol, if applicable). Ask about parking ratios and drive-thru restrictions.
-
Shell Condition: Identify whether you’re getting cold dark shell, gray shell, or second-gen restaurant space. The difference sets your budget.
-
Utility Capacity: Verify available gas line size/pressure, electrical service (amps/phase), and domestic water line size. Get this in writing.
-
Grease Interceptor: If none exists, clarify who pays for a new outside interceptor, who maintains it, and where it will fit on site.
-
Roof & Structural Loads: Type I hood, RTUs, walk-in coolers, and patio covers all have load implications. Confirm allowable loads early.
-
Schedule Risks: Ask the landlord for any known site plans, as-builts, and prior permits. Missing documents add weeks.
Step 2: Design & Permit Path (Who Submits What)
You’ll typically need: building permit, mechanical/electrical/plumbing (MEP) permits, health department plan review, and fire permits for hoods/suppression.
-
Core Submittals:
-
Architectural plans: life safety, exits, ADA restrooms, seating counts, finishes.
-
MEP engineering: load calcs, panel schedules, ductwork, gas sizing, plumbing risers, and fixture schedules.
-
Hood & suppression: Type I (grease) vs. Type II (heat/steam), duct routing, rooftop discharge, UL 300 wet chemical system.
-
Grease waste plan: interceptor sizing calculations, location, and access for pump-outs.
-
Health package: menu, equipment cut sheets with NSF/UL listings, finish schedule for floors/walls/ceilings in food zones.
-
Pro move: hold a brief pre-submittal call with the city plan reviewer. Ten minutes now saves ten days later.
Step 3: Utilities & Kitchen Infrastructure (Get the Bones Right)
Electrical
-
Service size: kitchens are power-hungry. Add up connected loads and diversity; avoid undersizing panels.
-
Equipment circuits: dedicated circuits for walk-ins, dish machines, and POS. Label everything; inspectors love clarity.
-
Emergency & egress lighting: test battery packs; required foot-candles along the exit path.
HVAC
-
Makeup air: must balance exhaust hoods. Negative buildings pull in dust and hot air—bad for comfort and doors that won’t close.
-
RTU placement: plan for roof curbs, seismic/structural details, and clearances around hood exhausts.
Gas
-
Sizing & pressure: wok ranges, fryers, and pizza ovens spike demand. Size the trunk, not just the tail ends.
-
Piping & ventilation: drip legs, shutoff valves, and clear access for each appliance.
Plumbing
-
Grease interceptor: right-size to your menu and volume; too small equals frequent pump-outs and violations.
-
Floor sinks & drains: indirect waste for ice machines, prep sinks, and dish machines. Maintain 1–2" air gaps.
-
Mop sinks & service sinks: required, and they can’t drain to the interceptor in some cases—check your plan review comments.
-
Water heater: pick recovery capacity for the rush, not the lull; dish machines need specific temps.
-
Backflow prevention: main service and dedicated devices where the city requires.
When you need a reliable trade partner for design-build coordination and inspections, bring in local specialists for commercial plumbing in lubbock, tx who know interceptor rules, backflow testing, and health-department expectations. Having the right plumber in your corner keeps your schedule (and CO) on track.
Step 4: Health Department Readiness (Menu Drives the Room)
-
Equipment list: match every item to a location on the plan with model numbers and sanitation listings.
-
Finish schedule: smooth, cleanable surfaces—no raw brick in splash zones, no wood where it will get wet.
-
Hand sinks: there must be enough (with soap/towels) to be “conveniently located” to work areas—often one more than you think.
-
Dish area: three-compartment sink or NSF dish machine with proper booster, drainboards, and separation from prep.
-
Cold & hot holding: provide cut sheets showing capacity and holding temps for your batch sizes.
Step 5: Inspections Timeline (Don’t Miss a Step)
Plan your build so inspectors see the right work at the right time. Skipping rough-ins equals tear-out.
| Milestone | What Inspectors Look For | Who Should Be On-Site |
|---|---|---|
| Underground plumbing | Interceptor connections, slope, venting | Plumber |
| Rough MEP | Hood duct/clearances, gas tests, electrical rough, drain/vent layout | GC + MEP subs |
| Above-ceiling | Fire stopping, duct hangers, plenum compliance | GC + Mechanical |
| Hood/suppression | UL 300 install, fusible links, nozzle placement, test | Fire contractor |
| Grease interceptor | Access, sizing, inlet/outlet, manholes | Plumber |
| Health pre-opening | Hand sinks, equipment fit-out, sanitizer, thermometers | Manager + GC |
| Final building/CO | Life safety, egress, signage, ADA, punch items | GC |
Tip: keep a printed “inspection binder” on site with approved plans, cut sheets, gas test certificates, backflow test, and any revisions. Inspectors appreciate organized jobs.
Step 6: ADA & Life Safety (Zero Surprises at CO)
-
Accessible route: from parking to the front door to the ordering counter and restrooms.
-
Restrooms: clearances at doors, grab bar locations, mirror and dispenser heights.
-
Egress: illuminated exit signs, panic hardware where required, and the right swing for occupant load.
-
Fire extinguishers: correct type (K-class near hoods) and properly mounted with tags.
Step 7: Procurement & Lead Times (What Delays Openings)
-
Hoods & suppression: 6–10 weeks if custom; order right after permit intake.
-
Walk-ins: confirm slab depressions, drains, and electrical locations before the box ships.
-
Interceptors: coordinate with site utilities—excavation and inspections can add a week.
-
Switchgear/panels: supply chains still fluctuate; lock specs early.
Step 8: Closeout & Training (Open Like a Pro)
-
Start-up & commissioning: RTUs, dish machine, hood/suppression, and water heater start-ups with checklists.
-
Backflow & grease service: log first tests and pump-out schedule; set digital reminders.
-
SOP binder: cleaning schedules, temperature logs, interceptor logs, pest control certificates, and a maintenance calendar.
-
Emergency plan: gas and water shutoffs labeled; staff trained on hood pull station and extinguisher use.
Common Pitfalls (And How to Dodge Them)
-
Unbalanced exhaust/makeup air: doors won’t close, AC struggles. Get a TAB (testing, adjusting, balancing) report.
-
Undersized water heater: dishes and hand sinks bottleneck during rush. Size for peak hour.
-
Missing hand sink or wrong location: instant health-department delay.
-
Skipping rough inspection photos: when ceilings close too soon, you’ll be opening them again.
-
Change orders from equipment swaps: any “Oh, we changed to a wok line” after permits means gas and hood redesign. Freeze the spec early.
A Simple Build-Out Timeline (High Level)
-
Weeks 0–2: Lease signed; schematic layout; utility verification.
-
Weeks 3–6: Full design; landlord approval; permit intake.
-
Weeks 7–10: Plan review; long-lead orders placed (hood, walk-in, interceptor).
-
Weeks 11–16: Demo & undergrounds; rough MEP; above-ceiling/firestop; hood install.
-
Weeks 17–20: Finishes; equipment set; start-ups; pre-health; final building & CO.
-
Week 21: Staff training, soft open.
(Timelines vary; inspections and long-leads are the swing factors.)
Opening a restaurant in Lubbock is absolutely doable on a tight timeline if you build around the inspections and the utilities. Size the infrastructure for your menu, lock specs early, and keep a clean inspection trail from rough-in to CO. Do those simple things well, and your opening week will be about food, not failures—and your guests will remember the flavor, not the smell of fresh caulk.

